-
01
ingest.shift
✓ SUCCEEDED
0.8 s
Plant Orchestrator · Pulled the shift build sequence, program control plan and qualified envelopes from MES: 412 bodies, four trim variants, weld schedule set W-rev 7, framing targets per station, paint colour blocks, torque specifications. Locked every safety-critical parameter as read-only.
-
02
twin.simulate
✓ SUCCEEDED
1 m 40 s
Vehicle-and-Line Twin · Simulated 18 candidate weld-sequence, framing-offset and booth-window combinations on the plant twin, ranked on predicted body geometry, expulsion risk at robot W-14, paint defect map and takt against launch cadence.
-
03
stamp.form
✓ SUCCEEDED
continuous
Stamp-and-Form · Blank feed on press line P-3 adjusted by 0.4 mm and lubricant dose raised 3 percent for the new coil lot as springback risk on the rear door inner climbed. Panel dimension held inside the window; genealogy handed to framing.
-
04
approve.human
◆ APPROVAL
3 m 12 s
Plant Orchestrator · Candidate #6 lowers weld current 2 percent and adds 20 ms hold on robot W-14 to cut predicted expulsion. Weld schedules are crash-safety critical and stay with a human, so the change was held for the body-shop launch engineer and approved at 06:14:52.
-
05
weld.join
✓ SUCCEEDED
continuous
Weld-and-Join · Approved schedule 7b applied on W-14. Current and force traces confirmed inside the window on the first 40 bodies; predicted expulsion risk fell from 0.31 to 0.06 and no geometry debt was introduced at the adjacent seams.
-
06
frame.geometry
✓ SUCCEEDED
continuous
Frame-and-Geometry · Framing station FS-1 offset corrected by 0.3 mm on the left B-pillar datum inside the qualified envelope as in-line measurement trended toward the tolerance edge. Gap-and-flush vision confirmed the correction on the next 25 bodies.
-
07
paint.finish
✓ SUCCEEDED
continuous
Paint-and-Finish · Booth B-2 humidity trimmed 2 points and airflow rebalanced for the dark-colour block as the defect model predicted dirt on horizontal panels. Film build held inside the window on the first colour block.
-
08
marriage.torque
✓ SUCCEEDED
continuous
Powertrain-and-Battery · Pack PK-1182 held at marriage after a torque-to-yield trace on fastener 7 fell outside the specification curve. Routed to rework with the trace attached; torque specification untouched, as always.
-
09
inspect.fuse
✓ SUCCEEDED
continuous
Quality-and-Anomaly · Gap-and-flush and paint-defect cameras, weld and torque traces and test results fused per body. Two paint dirt defects localised to booth B-2 zone 3 before the humidity trim took effect; both routed to spot repair, none escaped to final.
-
10
eol.release
✓ SUCCEEDED
2 m 05 s
EOL-and-Calibrate · End of line proved alignment, ADAS calibration, leak, brake, roll and functional tests on every vehicle; two ADAS retests sequenced inside takt. Shift 1 released with as-built records, approvals and dispositions written for the quality lead.